CNPE Consortium Completes Lifting of ITER Sector Module 9

2026-11-27 16:57 Nuclear fusion CNNC ITER

Recently, at the “International Thermonuclear Experimental Reactor” (ITER) site in “France”, the 7th “vacuum vessel sector module” of the “tokamak”—“Sector Module 9”—successfully completed its integral lifting and precise positioning; this was the first dual-side restricted lifting of an “International Thermonuclear Experimental Reactor” vacuum vessel module, completed by the “CNPE Consortium” leading and coordinating an international team. With this, “vacuum vessel module” assembly progress has exceeded three-quarters, and as installation of the remaining two modules advances, the “Sector Module Sub-Assembly contract” (SMSA contract) has entered its final phase.

The “vacuum vessel module” consists of 9 sector modules, each corresponding to 40 degrees. Since modules began entering the pit one after another, this was the first “dual-side restricted” lifting, in which a thousand-tonne-class module needed to complete descent, attitude adjustment, and precise positioning within a narrow space constrained by existing structures. “Sector Module Pre-Assembly Project Leader” Hu Xin stated that compared with previous installations, the most critical difference lies in the very narrow working space, which affects the lifting path, the module's in-air attitude, and the precision requirements for lifting. Moreover, the “Sector Module 9” components are more complex than before with uneven gravity distribution, and successfully entering the predetermined position required first mastering the accurate spatial relationship between the module to be installed and surrounding structures.

Regarding the refinement of lifting plan details and virtual simulation, “Measurement Engineer” Yuan Zhong explained that theoretically the “Sector Module 9” has approximately 50 mm clearance on each side with adjacent modules, but during actual lifting the module inevitably experiences slight verticality deviation and swaying, which may reduce the safety margin to 20 to 30 mm per side. This places higher demands on clearance optimization, virtual assembly, and center-of-gravity calculation. Before lifting, the project team led a measurement group from “Spain” to collect on-site structural geometric data, input it into the model for three-dimensional virtual assembly, and reasonably adjusted positions to increase clearance on both sides. Meanwhile, detailed center-of-gravity calculations were carried out and verticality deviation was strictly controlled within 6 mm to prevent interference during descent.

“Lifting Engineer” Zhu Xiaoqian introduced that the civil cable tray on the east side of the building is adjacent to the transfer path of “Sector Module 9”, also posing a collision risk. The team added multiple avoidance calculations and measured the module's free-state verticality after trial lifting, then compared the lifting path with the building environment again based on measured data to ensure no collision. Before the lifting operation, the “Construction Work Package” (CWP) department team, together with all relevant parties, verified the completion status of pre-installation work, closed out remaining technical issues, and conducted on-site verification of preparation conditions, covering close coordination of various professional processes including preliminary measurement, simulation, collision verification, calculation analysis, plan validation, as well as on-site monitoring, command, and practical operation.

It is understood that on November 25, “Sector Module 9” was transferred from the assembly hall to above the main pit, and began descending toward the predetermined position in the early hours of the next day. The lifting team operated step by step, while the “Construction Work Package” team simultaneously tracked load, pressure, clearance, and module tilt. Once abnormal readings appeared, they would jointly assess and determine countermeasures with the technical lead of the “ITER Organization” and the lifting engineer.

From pre-assembly to lifting and positioning, “Sector Module 9” took approximately 5.3 months, setting the shortest construction period to date. With this module in place, only the last two modules remain to be installed for “vacuum vessel sector module” installation, and they are the only two irregularly configured modules among the 9, meaning installation difficulty and precision requirements will further increase. The “CNPE Consortium” will continue to work hand in hand with the “ITER Organization” and all parties to tackle key challenges, jointly advance the project schedule, and drive the “Sector Module Sub-Assembly contract” to a successful conclusion.